Step 1.
Job begins


 
 
Step 2.
Week 1 to 2
Concrete Footings . . .


Step 3.
Week 1 to 2
Walls to DPC &, Damp Proof Membrane . . .


Step 4.
Week 1 to 2
Concrete Base, Outer Wall Progressed . . .


Step 5.
Week 1 to 2
Dwarf Walls Completed.


Step 6.
Week 3
Frames Fitted + 1st Fix Electrics*

* Optional Features


Step 7.
Week 3
Roof Glazing Installed . . .


Step 8.
Week 3
Side Glazing Installed.


Step 9.
Remaining Tasks:
(1 Day’s Work)
Plastering of Dwarf Walls/ Dry Lining of
House Wall*

* Optional Features


Step 10.
Remaining Tasks:
(1-2 Days)
Tiled Flooring*

* Optional Features


Step 11.
Remaining Tasks:
2nd Fix of Electrics (Couple of Hours)
Electric Convector Heater*

* Optional Features


Step 12.
Remaining Tasks:
Fan/Light Cluster*

* Optional Features

The schedule of work and time taken to complete a conservatory will inevitably vary from job to job but the above example is a typical and realistic outline of how your project might develop.